[Enzyme Finance] Grant Bi-Weekly Update 7/8/2024

Date: 7/8/2024

I. Executive Summary:

a) Roadmap Progress:

  • Code has been completed ,finalizing reviews.
  • Audit will start next week. (august 12th)
  • We started working on the wireframes for the frontend work
  • Frontend work should start next week
    b) Milestone/KPI Achievements: None
    c) Dune Dashboards: None/ Doesn’t apply

II. Current Progress:

  • Code has been completed ,finalizing reviews.
  • Audit will start next week. (august 12th)
  • We started working on the wireframes for the frontend work
  • Frontend work should start next week

III. Community Engagement: None

IV. Partnerships and Collaborations: None